EOV Update

UPDATE: We’re moving forward! The Mayor and ACC Commission unanimously approved our Special Use Permit! No need to do an expensive sidewalk along Timothy Road. We are very thankful to Josh Koons of Koons Environmental Design for developing and guiding the landscape plans through the ACC permitting process. The EOV Project Committee continues to work with Houser Walker Architects and Cloverleaf contractors refining the Design Development plans for the building. The first round of pricing by Cloverleaf came in over budget, but that is not unusual. We remain confident that with due diligence, and willingness to make trade-offs, construction will begin Spring 2018.